Monday, April 11, 2005

Day 38

Day 38, 2 hours of work done. We have the deck on boat 2. Used a new trick to try and get the deck to form better as the nails go in forming a better joint at the shear clamps. We placed two 3' long strips of scrap wood underneath 2 straps to hold the deck down in a nice and uniform fashion. This really helped hold the deck in place as we nailed and required less muscle while trying to form the deck.


Day 38 Photos
DAY38-001
DAY38-002
DAY38-003
DAY38-004
DAY38-005

0 Comments:

Post a Comment