Ok, on day 1 and 2 we started building the kayaks, total number of hours worked on these days was 51/2 What did we get done? Well, we unpacked all the materials and took an inventory of what we had, cleaned the shop, set up the string back, taped and glued the scarf joints for the side and bottom panels, glued the deck beams, and glued the sheer clamps.